Component |
Hours |
|
|
Wings Framework (2 X 2.5 hours) |
5 |
|
|
Flapperons Framework (4 X 0.5 hours) |
2 |
|
|
Horizontal Stabiliser Framework |
3 |
|
|
Elevator Framework |
3 |
|
|
Fin Framework |
0.5 |
|
|
Rudder Framework |
0.75 |
|
|
Wings Complete - skins, fuel tanks, flapperon hangers (2 X 8) |
16 |
|
|
Flapperons - skins, aeileron control attachments (4 X 0.75) |
3 |
|
|
Horizontal Stabiliser - skin |
2 |
|
|
Elevator - skin |
3 |
|
|
Fin - skin |
0.75 |
|
|
Rudder - skin |
1.5 |
|
|
Rear Fuselage Ribs |
2 |
|
|
Rear Fuselage - skin, frames, baggage compartment, seats rear |
20 |
|
|
Front Fuselage - cabin sides, floor, seats, cabin frame, firewall |
15 |
|
|
Controls - flapperon mixer box, rudder pedals, stick |
5 |
|
|
Cabin Doors (2 X 2) |
4 |
|
|
Undercarraige Installation - wheels, brakes |
4 |
|
|
Mount Engine |
1 |
|
|
Engine Connection - oil cooler, control cables, fuel line, exhaust, cabin heater, wiring |
6 |
|
|
Electrical Installation / Instruments |
4 |
|
|
Tail Assembly - fin, rudder, stabiliser, elevator, trim system |
6 |
|
|
Wing to Fuselage Assembly - lift struts, flapperons, control rods |
3 |
|
|
Miscellaneous - engine cowls, seats, seat belts, propeller, spinner, door fitment etc. |
15 |
|
|
Total Build Hours |
125.5 |
|